Per NEC 250.53(A)(2), if you driven a single ground rod and its resistance exceeds 25 ohms, you must add a second rod. However, most jurisdictions now require two rods regardless, spaced at least 6 feet apart, because achieving ≤25 ohms with one rod is rarely practical.
Since you've already driven one 8-foot rod, install a second rod at least 6 feet away. Both rods must be at least 8 feet long and in contact with the earth for their full length (NEC 250.53(F)).
Bond both rods together with a continuous #6 AWG copper conductor (or #4 AWG if more than one electrode conductor is used). Connect using approved clamps listed for direct burial.
If your local AHJ has adopted the 2017 or later NEC edition, note that GFCI protection is now required for detached structures supplied by a single feeder (NEC 250.4(A)(9) and 250.68(A) Exception).
Bottom line: Add the second rod. It's required in nearly all cases and costs little extra.