Depth: In Jacksonville (NEC and Florida follow the 2020 IRC), a 20A GFCI circuit to a shed requires minimum 18 inches of burial depth for rigid metal conduit (RMC), intermediate metal conduit (IMC), or PVC conduit. If using direct-burial cable (UF or USE), the minimum is 24 inches. Schedule 80 PVC requires 18 inches; Schedule 40 requires 18 inches only if GFCI-protected at the breaker.
Call Before You Dig: Yes. Florida 811 (call 811 or visit floridas811.com) is mandatory before any excavation. They’ll mark underground utilities within 2 business days. Failure to call can result in fines and dangerous strikes.
Additional Notes:
- GFCI protection is required at the shed (receptacles) and/or breaker.
- Use weatherproof boxes and covers rated for wet locations.
- If trench crosses property lines, verify local easement rules.
Bottom Line: Dig 18" minimum (conduit) or 24" (direct burial), and always call 811 first.