Order 3.0 cubic yards.
Math:
- Volume: 12 ft × 20 ft × 0.333 ft (4 in.) = 80 ft³
- Yards: 80 ft³ ÷ 27 ft³/yd³ = 2.96 yd³
- Waste/Over-excavation: Add 10% (standard for grade variance, spillage, pump loss) → 2.96 × 1.10 = 3.26 yd³
Order 3.0 yards (most plants sell in ¼ yd increments). If your subgrade is perfectly flat and compacted, 2.75 yd might squeak by, but 3.0 is the safe pro order. Short loads incur fees ($100–$200) and cold joints.
Specify to dispatch:
- Mix: 3,500–4,000 psi, ¾" aggregate, 4–5" slump (no water added on site).
- Air: 5–6% if freeze/thaw exposure (IRC R402.2).
- Reinforcement: #3 rebar 18" O.C. or 6x6-W2.9xW2.9 WWF, chairs to mid-depth (ACI 332).
- Vapor barrier: 10-mil poly under slab (IRC R506.2.3).
Pro tip: Have screed boards, bull float, and help ready before truck arrives.