No, you cannot legally or practically fill a 12-ft wall in a single pour. TMS 602 (ACI 530.1) Article 3.5 B limits maximum pour height to 4 ft (1.2 m) for standard grout lifts. A 12-ft pour generates ~750 psf lateral pressure at the base—enough to blow out face shells, displace reinforcement, or collapse the wall.
Legal/Code-Compliant Procedure (TMS 602 Art. 3.5):
- Lifts: Place grout in 4-ft maximum lifts.
- Time Limit: Complete each lift within 1.5 hours of batching (Art. 3.5 C).
- Consolidation: Mechanical vibration required for each lift (Art. 3.5 D). Insert vibrator 6–8 in. into previous lift to knit lifts. Re-vibrate after initial settlement (5–10 min).
- Cleanouts: Required for pours > 4 ft high (Art. 3.5 A). Install at base of every pour (every 4 ft) to remove mortar droppings, check alignment, and verify consolidation. Close before next lift.
- Grout Spec: Use coarse grout (3/8" aggregate) per ASTM C476. Slump 8–11 in. for vibration. Do not exceed 11 in. slump—segregation risk.
- Reinforcement: Verify vertical bars are tied/positioned per shop drawings before grouting. Horizontal bond beams must be grouted solid.
Practical Sequence:
- Day 1: Lay block to 4 ft. Install cleanouts. Vibrate Lift 1.
- Day 2: Lay next 4 ft. Cleanouts at 8 ft. Vibrate Lift 2 (penetrate Lift 1).
- Day 3: Lay top 4 ft. Final cleanouts. Vibrate Lift 3.
Inspector will check: Cleanout presence/closure, lift heights, vibrator on-site, grout tickets (slump/time), rebar position.
Bottom line: Three pours over three days. Skipping lifts or cleanouts = failed inspection and structural risk.