For a typical CMU (Concrete Masonry Unit) house, the standard inspection sequence from footing to tie beam is below. Always verify the exact required list on your permit card or local amendments—some jurisdictions combine or add inspections (e.g., termite treatment, slab moisture barrier).
1. Footing / Foundation Inspection
- When: After trenches are excavated, forms/rebar/chairs are placed, before concrete is poured.
- What they check: Depth/width per plans, soil bearing, rebar size/spacing/cover (ACI 318 / IRC R403), step footings, hold-down/anchor bolt templates.
2. Slab / Under-Slab Inspection (if slab-on-grade)
- When: After vapor barrier, sand/stone base, slab rebar/mesh, and plumbing rough-in (DWV pressure test) are complete, before slab pour.
- What they check: Vapor barrier laps/tape (IRC R506), rebar support/chairs, pipe protection/sleeves, termite treatment (if required locally).
3. Masonry Pre-Grout / "Cell" Inspection (Critical for CMU)
- When: After first few courses are laid, rebar dowels from footing are verified, vertical rebar is placed in cells, lintel steel is set, cleanouts are open at bottom of pour, before grout pump arrives.
- What they check: Rebar size/grade/spacing/lap splices (TMS 402/602 / IRC R606), cell alignment/cleanliness, grout space width (≥ 2" for coarse grout), lintel bearing/depth, anchor bolt/strap embedment.
4. Bond Beam / Tie Beam Inspection
- When: Formwork/block-outs for bond beam are in place, continuous horizontal rebar and stirrups/ties are tied, before grouting bond beam.
- What they check: Rebar continuity (corners, intersections), lap splices, stirrup spacing/hook embedment, anchor bolt/strap layout for roof/truss connection (IRC R606.11 / TMS 402), cleanouts.
5. Final Framing / Structural (Often combined with Tie Beam or separate)
- When: Roof trusses/rafters set, hurricane straps/clips installed, sheathing nailed (if required before dry-in), before roofing felt/dry-in.
- What they check: Truss-to-tie beam connections (straps per truss calcs/IRC R802.11), sheathing nailing schedule, gable end bracing.
Pro Tips
- Call 24 hrs ahead (or per local portal cutoff).
- Post permit & approved plans on site.
- Have cleanouts open for masonry pours—inspector will fail you if they can’t see bottom rebar.
- Grout tickets: Keep delivery tickets on site for inspector verification (slump, mix, time).
- Special Inspections: If engineered (